Resource
Spillway Options Report
This report outlines the repair works at Toddbrook dam to address damage to the auxiliary spillway following the incident that occurred on 1st August 2019. It describes the process taken to identify, evaluate and select a shortlist of sites for the spillway works, to be consulted on with the community and stakeholders. It describes criteria upon which the options have been reviewed and provides justification of these shortlisted concept options to be taken forward for final option selection and design. The design phase will include detailed development to work out the exact location, dimensions, construction and appearance of the final option based on further studies and analysis. The report explains what will happen in the next phases of the project.